19 May 2008
HULL TRUCK RAISES THE ROOF!

Construction of the new Hull Truck Theatre took a major step forwards this
week with the installation of steelwork which forms the roof structure.
Staff from Quarmby Construction Company
worked through the night on Monday to install the huge
beams.
The largest truss weighed 14 tons. Five other beams, each 17 metres long and weighing six tons, were also installed.
The steels were brought along Ferensway on low loaders, and a specialist 69-metre crane was set up in Portland Street and used to lift the steelwork into position.
Construction of the building is due
to be completed later this year and the building will open to the
public in spring 2009.
Images by Alice Mooney: The truss being lowered to the ground for adjustments
ready to lift on to the top of the building (above). Preparations underway
for positioning of the powerful crane (below left). The crane fully extended
(below right).

Media enquiries to Alice Mooney on 01482 325012 or Email alice@hulltruck.co.uk